Production

Current workload, queues, and machine allocation.

Open planner

Scheduled orders

3

Units in workload

3,800

No machine

6

Machines active

3 / 4

Machine allocation

Machine 172%

JO-2041 · 300 units

Machine 254%

JO-2042 · 750 units

Machine 361%

JO-2043 · 750 units

Machine 40%

Available

Production orders

Scheduled and unassigned work in one queue.

OrderCustomerMachineStatusDueUnits
JO-2041Northwind ApparelMachine 1In productionJul 26, 2026300
JO-2042Ember & OakMachine 2QueuedJul 27, 2026750
JO-2043Halcyon Coffee Co.Machine 3pausedJul 27, 2026750
JO-2044Morrow StudioNo machineQueuedAug 3, 2026200
JO-2045Pine & PeakNo machineQueuedJul 27, 2026600
JO-2046Sable GoodsNo machinepausedJul 29, 2026300
JO-2047Sable GoodsNo machinepausedJul 29, 2026300
JO-2048Sable GoodsNo machinepausedJul 29, 2026300
JO-2049Sable GoodsNo machinepausedJul 29, 2026300